Recommendations of the High Power Committee to review the duty hours of running & other safety related categories of staff – rosters of intensive category of staff
RBE No.67/2016
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
(RAILWAY BOARD)
No.2016/E(LL)/HPC/5
New Delhi
Dt.16.06.2016
The General Manager(P)
All India Railways & PUs
Sub: Recommendations of the High Power Committee to review the duty hours of running & other safety related categories of staff – rosters of intensive category of staff.
The High Power Committee, constituted to review the duty hours of running and other safety related categories of staff, had recommended on roster of intensive category of staff as under:
“The rosters for Intensive category staff should be made in such a way that they don’t work on all seven days in a week and also get a weekly rest of 40 hours minimum. Zonal Railways may be asked by the Ministry of Railways to modify their rosters for “Intensive”Category staff accordingly. A copy of the modified roster received by the committee from North Western Railway may be circulated to them along with this letter for guidance (Para 5.4)”.
The above recommendation has been duly considered by the Board and in modification of previous instructions on the subject, the following decision has been taken:
“Rosters may be revised on the basis of model roster of NWR to provide better quality of periodical rest to affected categories of staff.”
A Copy of the model roster from NWR recommended by the committee is enclosed. Railways may consider the feasibility of adopting the above roster without creating additional posts so that they get proper rest in a week.
The existing provisions of the Railways Act, 1989 and Railway Servants (Hours of Work & period of Rest) Rules 2005 will continue to be applicable.
This issues with the concurrence of Finance directorate of the Ministry of Railways.
Please acknowledge the receipt.
DA:As above.
(D.V.Rao)
Director Estt.(LL)
Railway Board
Annexure – XI
Proposed roster received from North Western Railway for “Intensive” Category Staff
S.No |
Days |
Employee A |
Employee B |
Employee C |
Employee D |
||||||||
|
|
From to Hours |
Duty Hours |
Rest Hours |
From to Hours |
Duty Hours |
Rest Hours |
From to Hours |
Duty Hour |
Rest Hours |
From to Hours |
Duty Hours |
Rest Hours |
1 |
Sunday |
0-6 |
6 |
12 |
18-24 |
6 |
36 |
12-18 |
6 |
12 |
6-12 |
6 |
12 |
2 |
Monday |
Rest |
|
42 |
18-24 |
6 |
18 |
12-18 |
6 |
18 |
06-12 |
6 |
18 |
3 |
Tuesday |
0-6 |
6 |
|
18-24 |
6 |
18 |
12-18 |
6 |
18 |
Rest |
|
42 |
4 |
Wednesday |
0-6 |
6 |
18 |
18-24 |
6 |
18 |
Rest |
6 |
42 |
06-12 |
6 |
|
5 |
Thursday |
0-6 |
6 |
18 |
Rest |
|
42 |
12-18 |
6 |
|
06-12 |
6 |
18 |
6 |
Friday |
0-6 |
6 |
18 |
18-24 |
6 |
|
12-18 |
6 |
18 |
06-12 |
6 |
18 |
7 |
Saturday |
0-6 |
6 |
18 |
18-24 |
6 |
18 |
12-18 |
6 |
18 |
06-12 |
6 |
18 |
|
Total |
—– |
36 |
—– |
——- |
36 |
—– |
——– |
36 |
—- |
——– |
36 |
—– |
Note: 1. One additional rest giver will be required with two spare working days.
2. A Will pick up roster of B,B will pick up roster of C,C will Pickup roster of D & D will pickup roster of A. After every week no body remains on duty continues for day/night.
source: AIRF
Ram Nagina says
It was very necessary due to employees who work in Intensive category give more attention than Continuous category but they do not have weekly Rest, which is a necessity of an employee to prepare for next week and to care to their family. Thanks to all who work hard for this.